Regional Connector Transit Corridor Project

Little Tokyo Station site
Little Tokyo Station site
TBM Angeli in lauch shaft
TBM Angeli in lauch shaft
TBM Angeli in launch shaft 2
TBM Angeli in launch shaft 2
2nd Broadway wall rebar
2nd Broadway wall rebar
Precast segmental tunnel lining rebar
Precast segmental tunnel lining rebar
Polypropylene fiber for tunnel lining fire protection
Polypropylene fiber for tunnel lining fire protection
TBM Angeli breakthrough last 2nd-Hope station
TBM Angeli breakthrough last 2nd-Hope station
Preparing for 2nd breakthrough at 2nd-Hope station
Preparing for 2nd breakthrough at 2nd-Hope station
Removing Temporary Steel Rings
Removing Temporary Steel Rings
Pecast segmental tunnel lining with conveyor belt
Pecast segmental tunnel lining with conveyor belt
Completed Tunnel
Completed Tunnel
Crosspassage Construction
Crosspassage Construction
Tunel with walkway
Tunel with walkway
Completed tunnel with track
Completed tunnel with track
Tunnel Omega Seal
Tunnel Omega Seal
2nd-Hope station construction
2nd-Hope station construction
SEM Cavern - Center drift excavation
SEM Cavern – Center drift excavation
SEM Cavern - Center drift excavation
SEM Cavern – Center drift excavation
SEM Cavern - Demolition of center walls
SEM Cavern – Demolition of center walls
SEM Cavern excavation near completion
SEM Cavern excavation near completion
SEM Cavern - Looking toward 2nd-Broadway Station
SEM Cavern – Looking toward 2nd-Broadway Station
SEM cavern HDPE installation
SEM cavern HDPE installation
SEM cavern rebar installation
SEM cavern rebar installation
SEM cavern concrete work
SEM cavern concrete work
SEM cavern construction
SEM cavern construction
SEM cavern crown construction
SEM cavern crown construction
SEM cavern contact grouting
SEM cavern contact grouting
2nd Hope station rendering 2
2nd Hope station rendering 2
2nd Hope station rendering
2nd Hope station rendering
SEM cavern crossover completion
SEM cavern crossover completion
2nd-Hope station construction
2nd-Hope station construction
2nd-Hope Station Construction
2nd-Hope Station Construction
2nd Hope elevator headhouse
2nd Hope elevator headhouse
2nd-Hope station construction
2nd-Hope station construction
2nd Broadway Station rendering
2nd Broadway Station rendering
2nd-BroadwayStationConstruction
2nd-BroadwayStationConstruction
2nd-Broadway station construction
2nd-Broadway station construction
2nd-Broadway station construction
2nd-Broadway station construction
2nd-Broadway station roof construction
2nd-Broadway station roof construction
2nd Broadway utility hanging
2nd Broadway utility hanging
2nd Broadway embedded conduits
2nd Broadway embedded conduits
2nd Broadway starter bars for future overbuild
2nd Broadway starter bars for future overbuild
2nd Broadway site overview
2nd Broadway site overview
Little Tokyo Art Disctrict Station rendering
Little Tokyo Art Disctrict Station rendering
Little Tokyo Station platform
Little Tokyo Station platform
Flower Street excavation utility hanging
Flower Street excavation utility hanging
Flower street muck shaft
Flower street muck shaft
Alameda embedded track construction
Alameda embedded track construction
1st Street portal construction
1st Street portal construction
Floating slab track production
Floating slab track production
Floating slab track installation
Floating slab track installation
Floating slab track installation
Floating slab track installation
Floating slab track installation
Floating slab track installation
Low vibration track (LVT) construction
Low vibration track (LVT) construction
Low vibration track (LVT) Installation
Low vibration track (LVT) Installation
Low vibration track (LVT) completion
Low vibration track (LVT) completion

The Regional Connector Transit Corridor is an underground light rail link that goes through the downtown Los Angeles and connects the Metro Gold Line to the Metro Blue Line and future Expo Line via Flower Street and 2nd Street. The project consists of approximately 1.9 miles of cut-and-cover and 21-foot diameter twin bored tunnels, three underground stations, a sequential excavation method cavern (60 feet wide, 38 feet high, and 300 feet long), and U-section guideway. The project has been successfully completed and opened to public in June 2023.

VNTU Inc. is serving as a subconsultant to the Connector Partnership Joint Venture (CPJV), led by AECOM and WSP, to support LA Metro to review all the design and construction submittals of this complex subway project. Mr. Vu is serving as the lead structural and geotechnical reviewer to review design of bored tunnels, cut-and-cover tunnels, underground stations, SEM cavern, crosspassages, support of excavation, permeation and compensation grouting for building protection, building underpinning, and geotechnical reports submitted by the design-builder during the final design phase. During the bidding and preliminary engineering phases (while he was working at AECOM and Jacobs Associates), he worked on updating geotechnical baseline report and support of excavation drawings; prepared the building and adjacent structure protection report; conducted field visits to evaluate and document existing conditions of critical structures along bored tunnel sections; performed analyses to assess potential impacts of the bored tunnels to the adjacent buildings and utilities; and developed mitigation plan and instrumentation drawings.